Viewing 1 reply thread
  • Author
    Posts
    • #57236
      Unregistered-Debbie
      Guest

      We have gutted a bathroom and are ready to hang drywall. We are also going to install ceramic tile shower walls and flooring. Which do I do first – hang the drywall or put the cementboard on the floor?

    • #273211
      Faron79
      Participant

      Hi Debbie,
      You MUST put up cement board on the walls too, if you’re gonna have a tiled shower-stall!! I believe it’s required as code. Only the actual shower-stall area has to have cement board behind it, but doublecheck with some tilers/builders.
      It’s also very heavy!! Have some friends handy!!
      >>> Ask your tile retailer what should be tiled first. Also inquire about your subfloor requirements. Most remodels DON’T have a stiff-enough subfloor!! Usually you have to lay additional plywood.
      >>> DON’T skimp here…you’re not gonna want to see cracking grout lines/tiles because your floor flexes too much!!
      Thanks!
      Faron

Viewing 1 reply thread
  • You must be logged in to reply to this topic.