      We are adding on a master bathroom ourselves and subing out the plumbing, electrical, etc. It would be great to have a sequence of events so that I can schedule everything properly. Do you have information that I can follow to help me accomplish this goal.

    • #284532
      MyPlumbingsupplier
      Participant

      The best way to proceed is to first ask your contractor what time line he has in mind, this will allow you to make your schedule. If you’re going to purchase the fixtures yourself, you should allow a few weeks for delivery just incase something is back order. I recommend checking out http://www.HomeCenter.com for your fixtures. The prices are very good and so is their inventory. In most cases you will save a lot of money buying the material yourself.

      Your contract will:

      Gut the bathroom.
      Install new rough in valves for faucets.
      drywall/green board the walls.
      Set tile
      Install fixtures

      You really want to have the fixtures there before they need them so you don’t hold up your project.

      Dominic Anfossi
      Visit http://www.MyPlumbingSupplier.com for more tips and product information.